The tractors began moving dirt for our new K-8 facility on May 1, 2006 and the dirt pad for the new building was completed by July 28.
Raising the Building
Erection of the steel building began on August 14 and was completed by the end of September. This was quickly followed by roof and utility installation, pouring of the first floors and the laying of block for the elementary wing corridor.